Human Spaceflights

International Flight-No. 260

STS-126

Endeavour (22)

USA

Patch STS-126 Patch STS-126 ULF-2

hi res version (561 KB)

hi res version (378 KB)

Launch, orbit and landing data

Launch date:  15.11.2008
Launch time:  00:55 UT
Launch site:  Cape Canaveral (KSC)
Launch pad:  39-A
Altitude:  51,67°
Inclination:  349 - 354 km
Landing date:  30.11.2008
Landing time:  21:25 UT
Landing site:  Edwards AFB
Crew STS-126

hi res version (979 KB)

alternate crew photo

alternate crew photo

Crew

No.   Surname Given name Job Flight No. Duration Orbits
1 USA  Ferguson  Christopher John  CDR 2 15d 20h 30m  249 
2 USA  Boe  Eric Allen  PLT 1 15d 20h 30m  249 
3 USA  Stefanyshyn-Piper  Heidemarie Martha  MSP 2 15d 20h 30m  249 
4 USA  Pettit  Donald Roy  MSP 2 15d 20h 30m  249 
5 USA  Bowen  Stephen Gerard  MSP 1 15d 20h 30m  249 
6 USA  Kimbrough  Robert Shane  MSP 1 15d 20h 30m  249 
7 USA  Magnus  Sandra Hall  Flight Engineer 2

 

Crew seating arrangement

Launch
1  Ferguson
2  Boe
3  Pettit
4  Bowen
5  Stefanyshyn-Piper
6  Kimbrough
7  Magnus
Space Shuttle cockpit
Landing
1  Ferguson
2  Boe
3  Kimbrough
4  Bowen
5  Stefanyshyn-Piper
6  Pettit
7  Chamitoff

Backup Crew

No.   Surname Given name Job
7 USA  Stott  Nicole Marie Passonno  Flight Engineer

Flight

Launch from Cape Canaveral (KSC); landing on the Edwards AFB; ISS-ULF-2 MPLM Leonardo.

Following a two day solo flight Endeavour docked to the ISS on 16.11.2008. Common work with the ISS expedition 18. Transfer Magnus to ISS and Chamitoff to the STS-126-crew.

First EVA by Stefanyshyn-Piper and Bowen on 18.11.2008 (6h 52m) to replace a depleted nitrogen tank and a device used to help the flow of coolant from the truss, the backbone of the station. They also removed thermal covers from the Japanese Kibo module to inspect the berthing mechanism where the module's exposed facility will be installed during the STS-127 mission in 2009. They also started inspecting, cleaning and lubricating the starboard SARJ and begin replacing 11 of 12 trundle bearings. One was replaced during the STS-124 mission in June 2008. About halfway into the spacewalk, one of the grease guns that Stefanyshyn-Piper was preparing to use on the SARJ released some braycote grease into her crew lock bag, which is the tool bag the spacewalkers use during their activities. As she was cleaning the inside of the bag, it drifted away from her and toward the aft and starboard portion of the International Space Station. Inside the bag were two grease guns, scrapers, several wipes and tethers and some tool caddies. Bowen then shared bag and equipment with her.

On flight day 6 there were no EVA-activities and the crew installed two crew quarters racks into the Harmony node, and installed a rack with equipment to be returned to Earth into the MPLM (Leonardo). The crew also began working on activating the Water Recovery System, so that samples of water from two areas could be taken and returned to Earth with Endeavour.

Second EVA by Stefanyshyn-Piper and Kimbrough on 20.11.2008 (6h 45m) to relocate two equipment carts, setting the stage for the installation of the starboard S6 truss (scheduled for February 2009). The spacewalkers also lubricated the end effector, or hand, of the Canadarm2, the station's robotic arm. They also continued lubricating the starboard SARJ and replacing trundle bearings.

On flight day 8 Fincke and Magnus tested latches on the Exposed Facility Berthing Mechanism for the Japanese Kibo laboratory. Magnus continued with the installation of the Total Organic Carbon Analyzer (TOCA), while engineers on the ground worked through troubleshooting of the Urine Processor Assembly. The component ran initially on Thursday evening, but shut itself down during that initial test, and shut down again the following morning after two hours of operations.

Third EVA by Stefanyshyn-Piper and Bowen on 22.11.2008 (6h 57m) to complete starboard SARJ cleaning, lubricating and trundle bearing work.

The two crews (Station and Shuttle) continued transfer operations on Flight day 10, and Fincke and Pettit worked together to reconfigure the Urine Processing Assembly (UPA) to try to dampen any vibration that may be contributing to the unit's shutting down prematurely. The unit had continued to operate sporadically, shutting itself down after two to three hours of operations, and the engineers on the ground were still evaluating the possible causes and solutions.

Fourth and final EVA by Bowen and Kimbrough on 24.11.2008 (6h 07m) to remove several thermal covers on the port SARJ. Kimbrough lubricated the port SARJ, while Bowen reinstalled the thermal insulation covers (removed on first EVA) on Kibo. He then installed two GPS antennas on Kibo's logistics module, while Kimbrough installed a new TV camera on the truss. Meanwhile the managers on the groud had decided to extend Endeavours mission to allow the crews more time to resolve the issues with the Urine Processing Assembly. And the UPA finally appeared to be functioning normally after the modifications performed by the crew on orbit.

Due to bad weather at the primary landing site at Cape Canaveral (KSC) the Endeavour landed with two orbits delay at the Edwards AFB.

Photos / Drawings

Space Shuttle Multi-Purpose Logistics Module (MPLM)
ISS after STS-126 STS-126 on launch pad
STS-126 launch EVA Bowen
EVA Kimbrough STS-126 in orbit
STS-126 landing

©      

Last update on December 15, 2008.

Back to homepage SPACEFACTS